18-Sep-08 - Hydroelectric power station el Platanal – up and running
Management, supervision, commissioning and start up of the project was assigned to ARPL. The station is located in the Cañete river basin and will produce 220 MW. Recognized companies are involved in ... (more...)
 
18-Sep-08 - Sixth combined grinding of cement
On August 2008, ARPL and Cemento Andino achieved the startup of the sixth cement mill. The purpose of this project is to expand the present grinding capacity, satisfying the increasing demand of cemen... (more...)
 
18-Sep-08 - Atocongo plant enlargement
Due to the increasing demand, Cementos Lima has decided to increase its plant capacity from 10,700 to 15,000 tons of clinker per day, and ute other projects in accordance with its environment and soci... (more...)
 
18-Sep-08 - Bagging and dispatch capacity enlargement Lines 5 and 6
As part of its investment project and due to the increase of production, Cementos Lima has decided to add two new Haver amp; Boecker bagging machines to feed four lines for trucks loading. The projec... (more...)
 
18-Sep-08 - Kiln III Control System Modernization 2nd stage
The objective of this project is to ensure the continuous operation of Cemento Andino’s kiln III avoiding unexpected stops. This modern control system permits an adequate control of production paramet... (more...)
 
 
 
Loading...
Back to News
Atocongo plant enlargement
Due to the increasing demand, Cementos Lima has decided to increase its plant capacity from 10,700 to 15,000 tons of clinker per day, and ute other projects in accordance with its environment and social development policy. The project has started on January 2007 and it is estimated to finish around December 2010. At the present, August 2008, the ution of the project reports a real progress of 4.04[%] in correspondence with 5.76[%] programmed. The activities carried out so far are the evaluations of proposals of mechanical supplies such as preheater, kiln and heat exchanger which are associated with the structural design and, therefore, with the construction kickoff.
SOURCE:  
Av. Carlos Villaran N° 508,
4° piso Lima 13 Perú .
Tel. (511) 265 7272 Fax (511) 4702339
www.arpl.com
Last updated 01/28/2008